Pelletizing Plant
|
Date |
P.No |
Project |
Capacity |
Method of production |
Description
Poolad partners |
1984-1989 |
395 |
Ahwaz |
2*2.5 MTPY |
LURGI |
LURGI co. |
1996
2000
2002 |
333 |
Gol-E-Gohar |
3.2 MTPY |
LURGI |
in 3 stages with:
BATEMAN (1996)
KOBE STEEL (2000) (ALLIS CHALMERS)
IDRO and DANIELI (2002) |
2003 |
382 |
Ardakan |
3.4 MTPY |
ALLIS CHALMERS |
KOBE |
2004 |
391 |
Mobarakeh |
5 to 7 MTPY |
LURGI |
ITALIAN PIENTI |
2005 |
395 (x) |
Khuzestan |
6.8 MTPY |
LURGI |
HATCH
based on 2*2.5 MTPY, improved
to 2*3.4 MTPY
and expandable to 7.2 MTPY |
2009 |
415 |
Sechahun |
5 MTPY |
ALLIS CHALMERS |
KDD, MCC-CIE, NICC |
|